Turnkey Automated Assembly Cell for High-Volume EV Traction Motors
01 / THE PRODUCTION CHALLENGE

What needed to be engineered.

A leading electric powertrain manufacturer required a multi-station automated line to assemble stator cores and insert pre-formed hairpin copper windings under a strict 45-second takt time.

The process demanded zero manual handling deformation, ±12 µm radial insertion clearance, and 100% inline electrical insulation resistance (dielectric) testing before downstream varnishing.

02 / TECHNICAL ARCHITECTURE & SOLUTION

How Draftdu solved it.

Draftdu engineered a synchronized 6-station rotary indexing assembly cell featuring servo-driven precision insertion tooling, a 6-axis robotic arm with custom vision-guided EOAT for hairpin alignment, and an automated high-potential (Hi-Pot) electrical test station.

We implemented closed-loop force-displacement monitoring on every insertion press and programmed custom safety interlocks with Omron light curtains and Siemens S7-1500 PLC control.

03 / QUANTIFIABLE OUTCOME

Measurable shop-floor results.

Cycle time was reduced from 68 seconds to 43 seconds (36% improvement), achieving consistent ±10 µm radial concentricity. Over 150,000 stator assemblies have been manufactured with zero field dielectric failures.

04 / TECHNOLOGIES & DIRECTIVES DEPLOYED

Engineering stack

6-Axis Robotics Servo Press Tooling Telecentric Vision Alignment Hi-Pot Dielectric Testing Siemens S7-1500 PLC Rotary Indexer